Item L-108 Underground Power Cable for Airports
DESCRIPTION
108-1.1 This item shall consist of furnishing and installing power cables direct buried and furnishing and/or installing power cables within conduit or duct banks in accordance with these specifications at the locations shown on the plans. It includes excavation and backfill of trench for direct-buried cables only. Also included are the installation of counterpoise wires, ground wires, ground rods and connections, cable splicing, cable marking, cable testing, and all incidentals necessary to place the cable in operating condition as a completed unit to the satisfaction of the Engineer. This item shall not include the installation of duct banks or conduit, trenching and backfilling for duct banks or conduit, or furnishing or installation of any cable for FAA facilities. Requirements and payment for trenching and backfilling for the installation of underground conduit and duct banks is covered under Item L-110 “Airport Underground Electrical Duct Banks and Conduits.”
EQUIPMENT AND MATERIALS
108-2.1 GENERAL.
a.Airport lighting equipment and materials covered by Federal Aviation Administration (FAA) specifications shall be approved under the Airport Lighting Equipment Certification Program described in Advisory Circular (AC) 150/5345-53, current version.b.All other equipment and materials covered by other referenced specifications shall be subject to acceptance through manufacturer’s certification of compliance with the applicable specification, when requested by the Engineer.
c.Manufacturer’s certifications shall not relieve the Contractor of the Contractor’s responsibility to provide materials in accordance with these specifications and acceptable to the Engineer. Materials supplied and/or installed that do not materially comply with these specifications shall be removed, when directed by the Engineer and replaced with materials, which do comply with these specifications, at the sole cost of the Contractor.
d. All materials and equipment used to construct this item shall be submitted to the Engineer for approval prior to ordering the equipment. Submittals consisting of marked catalog sheets or shop drawings shall be provided. Submittal data shall be presented in a clear, precise and thorough manner. Original catalog sheets are preferred. Photocopies are acceptable provided they are as good a quality as the original. Clearly and boldly mark each copy to identify pertinent products or models applicable to this project. Indicate all optional equipment and delete non-pertinent data. Submittals for components of electrical equipment and systems shall identify the equipment for which they apply on each submittal sheet. Markings shall be boldly and clearly made with arrows or circles (highlighting is not acceptable). Contractor is solely responsible for delays in project accruing directly or indirectly from late submissions or resubmissions of submittals.
e.The data submitted  shall be sufficient, in the opinion of the Engineer, to determine compliance with  the plans and specifications. [The Contractor’s submittals shall be neatly bound  in a properly sized 3-ring binder, tabbed by specification section.] The Engineer  reserves the right to reject any and all equipment, materials or procedures, which,  in the Engineer’s opinion, does not meet the system design and the standards and  codes, specified herein.
f.All equipment  and materials furnished and installed under this section shall be guaranteed against  defects in materials and workmanship for a period of at least [twelve (12) months]  from final acceptance by the Owner. The defective materials and/or equipment shall  be repaired or replaced, at the Owner’s discretion, with no additional cost to the  Owner. The Contractor shall be responsible to maintain an insulation resistance  of 50 megohms minima, (1000 V megger) with isolation transformers connected in new  circuits and new segments of existing circuits through the end of the contract warranty  period.
The engineer should specify the form in which submittals  are to be received and number of copies.
The length of time for guarantee of materials and  workmanship should be as stated in the contract between the owner and contractor  and the contract special provisions.
108-2.2 CABLE.
Underground cable for airfield  lighting facilities (runway and taxiway lights and signs) shall conform to the requirements  of AC 150/5345-7, Specification for L-824 Underground Electrical Cable for Airport  Lighting Circuits. Conductor sizes noted above shall not apply to leads furnished  by manufacturers on airfield lighting transformers and fixtures.
Wire  for electrical circuits up to 600 volts shall comply with Specification L-824  and/or Federal Specification J-C-30 and shall be type THWN-2.
Cable type,  size, number of conductors, strand and service voltage shall be as specified on  the plans.
108-2.3 BARE COPPER WIRE (COUNTERPOISE, BARE COPPER WIRE  GROUND AND GROUND RODS).
Wire for counterpoise or ground  installations for airfield lighting systems shall be No. 6 AWG solid for counterpoise  and or No. 6 AWG stranded for ground wire conforming to ASTM B 3 and ASTM B 8, and  shall be [bare copper wire] [tinned copper]conforming to the requirements of ASTM D 33.
Ground rods  shall be [solid stainless steel] [copper]  or [copper-clad steel]. The ground rods shall be of the length and diameter  specified on the plans, but in no case shall they be less than 8-feet (240 cm) long nor less than 5/8 in (15 mm) in diameter.
Engineer should  evaluate the soils in the vicinity of proposed counterpoise and ground rod installations  and determine if soil conditions would adversely affect copper. Engineer shall specify  the type of ground rod and counterpoise wire to be installed in consideration of  the soil conditions. If tinned copper counterpoise or ground wire is specified,  include requirement for UL listing.
108-2.4 CABLE CONNECTIONS.
In-line connections of underground  primary cables shall be of the type called for on the plans, and shall be one of  the types listed below. No separate payment will be made for cable connections.
a. The Cast Splice.A cast splice, employing a plastic mold and using epoxy resin equivalent  to that manufactured by Minnesota Mining and Manufacturing Company, “Scotchcast”  Kit No. 82--B, or as manufactured by Hysol® Corporation, “Hyseal Epoxy Splice” Kit  No. E1135, or equivalent, is used for potting the splice is acceptable.
b. The Field-attached Plug-in Splice.Figure 3 of AC 150/5345-26, Specification for L-823 Plug and Receptacle,  Cable Connectors, employing connector kits, is acceptable for field attachment to  single conductor cable. It shall be the Contractor’s responsibility to determine  the outside diameter of the cable to be spliced and to furnish appropriately sized  connector kits and/or adapters and heat shrink tubing with integral sealant.
c. The Factory-Molded Plug-in Splice.Specification for L-823 Connectors, Factory-Molded to Individual Conductors,  is acceptable.
d. The Taped or Heat-Shrinked Splice.Taped splices employing field-applied rubber, or synthetic rubber tape  covered with plastic tape is acceptable. The rubber tape should meet the requirements  of ASTM D 4388 and the plastic tape should comply with Mil Spec. MIL-I-24391 or  Fed. Spec. A-A-55809. Heat shrinkable tubing shall be heavy-wall, self-sealing tubing  rated for the voltage of the wire being spliced and suitable for direct-buried installations.  The tubing shall be factory coated with a thermoplastic adhesive-sealant that will  adhere to the insulation of the wire being spliced forming a moisture- and dirt-proof  seal. Additionally, heat shrinkable tubing for multi-conductor cables, shielded  cables, and armored cables shall be factory kits designed for the application. Heat  shrinkable tubing and tubing kits shall be manufactured by Tyco Electronics/ Raychem  Corporation, Energy Division, or approved equivalent.
In all the above cases, connections of cable  conductors shall be made using crimp connectors using a crimping tool designed to  make a complete crimp before the tool can be removed. All L-823/L-824 splices and  terminations shall be made in accordance with the manufacturer’s recommendations  and listings.
All connections of counterpoise, grounding conductors  and ground rods shall be made by the exothermic process or approved equivalent,  except the base can ground clamp connector shall be used for attachment to the base  can. All exothermic connections shall be made in accordance with the manufacturer’s  recommendations and listings.
108-2.5 SPLICER QUALIFICATIONS.
Every airfield lighting cable splicer shall be qualified in making cable splices and terminations on cables rated above 5,000 volts AC. The Contractor shall submit to the Engineer proof of the qualifications of each proposed cable splicer for the cable type and voltage level to be worked on. Cable splicing/terminating personnel shall have a minimum of three (3) years continuous experience in terminating/splicing medium voltage cable.
108-2.6 CONCRETE.
Concrete for cable markers shall conform to Specification Item P-610, “Structural Portland Cement Concrete.”
108-2.7 FLOWABLE BACKFILL.
Flowable material used to backfill trenches for power cable trenches shall conform to the requirements of Item P-153 “Controlled Low Strength Material”.
108-2.8 CABLE IDENTIFICATION TAGS.
Cable identification tags shall be made from a non-corrosive material with the circuit identification stamped or etched onto the tag. The tags shall be of the type as detailed on the plans
108-2.9 TAPE.
Electrical tapes shall be Scotch Electrical Tapes – number Scotch 88 (1-1/2” wide) and Scotch 130C linerless rubber splicing tape (2” wide), as manufactured by the Minnesota Mining and Manufacturing Company, or approved equivalent.
108-2.10 ELECTRICAL COATING.
Scotchkote™ shall be as manufactured by Minnesota Mining and Manufacturing Company, or approved equivalent.
108-2.11 EXISTING CIRCUITS.
Whenever the scope of work requires, connection to an existing circuit, the circuit’s insulation resistance shall be tested, in the presence of the Engineer. The test shall be performed in accordance with this item and prior to any activity affecting the respective circuit. The Contractor shall record the results on forms acceptable to the engineer. When the work affecting the circuit is complete, the circuit’s insulation resistance shall be checked again, in the presence of the Engineer. The Contractor shall record the results on forms acceptable to the engineer. The second reading shall be equal to or greater than the first reading or the Contractor shall make the necessary repairs to the circuit to bring the second reading above the first reading. All repair costs including a complete replacement of the L-823 connectors, L-830 transformers and L-824 cable, if necessary, shall be borne by the Contractor. All test results shall be submitted in the Operation and Maintenance (O&M) Manual.
CONSTRUCTION METHODS
108-3.1 GENERAL.
The Contractor shall install the specified  cable at the approximate locations indicated on the plans. Unless otherwise shown  on the plans, all cable required to cross under pavements expected to carry aircraft  loads shall be installed in concrete encased duct banks. Wherever possible, cable  shall be run without splices, from connection to connection.
Cable connections between lights will be permitted  only at the light locations for connecting the underground cable to the primary  leads of the individual isolation transformers. The Contractor shall be responsible  for providing cable in continuous lengths for home runs or other long cable runs  without connections, unless otherwise authorized in writing by the Engineer or shown  on the plans.
In addition to connectors being installed at  individual isolation transformers, L-823 cable connectors for maintenance and test  points shall be installed at locations shown on the plans. Cable circuit identification  markers shall be installed on both sides of the L-823 connectors installed or at  least once in each access point where L-823 connectors are not installed.
Engineer should determine and specify on the plans an adequate number of locations for installing L-823 connectors to provide maintenance and test points.
Provide not less than 3 feet of cable slack on each side of all connections, isolation transformers, light units, and at points where cable is connected to field equipment. Where provisions must be made for testing or for future above grade connections, provide enough slack to allow the cable to be extended at least 1 ft vertically above the top of the access structure. This requirement also applies where primary cable passes through empty base cans, junction and access structures to allow for future connections, or as designated by the Engineer.
108-3.2 INSTALLATION IN DUCT BANKS OR CONDUITS.
This item includes  the installation of the cable in duct banks or conduit as described below. The maximum  number and voltage ratings of cables installed in each single duct or conduit, and  the current-carrying capacity of each cable shall be in accordance with the latest  National Electric Code, or the code of the local agency or authority having jurisdiction.
The Contractor shall make no connections or  splices of any kind in cables installed in conduits or duct banks.
Unless otherwise designated in the plans, where  ducts are in tiers, use the lowest ducts to receive the cable first, with spare  ducts left in the upper levels. Check duct routes prior to construction to obtain  assurance that the shortest routes are selected and interferences are avoided.
Duct banks or conduits shall be installed as  a separate item in accordance with Item L-110, “Airport Underground Electrical Duct  Banks and Conduit.” The Contractor shall run a mandrel through duct banks or conduit  prior to installation of cable to insure that the duct bank or conduit is open,  continuous and clear of debris. Mandrel size shall be compatible with conduit size.  The Contractor shall swab out all conduits/ducts and clean base can, manhole, etc.  interiors 
IMMEDIATELY
prior to pulling cable. Once cleaned and swabbed the base  cans and all accessible points of entry to the duct/conduit system shall be kept  closed except when installing cables. Cleaning of ducts, base cans, manholes, etc.  is incidental to the pay item of the item being cleaned. All raceway systems left  open, after initial cleaning, for any reason shall be recleaned at the Contractor’s  expense. All accessible points shall be kept closed when not installing cable. The  Contractor shall verify existing ducts proposed for use in this project as clear  and open. The Contractor shall notify the Engineer of any blockage in the existing  ducts. The cable shall be installed in a manner to prevent harmful stretching of  the conductor, injury to the insulation, or damage to the outer protective covering.  The ends of all cables shall be sealed with moisture-seal tape providing moisture-tight  mechanical protection with minimum bulk, or alternately, heat shrinkable tubing  before pulling into the conduit and it shall be left sealed until connections are  made. Where more than one cable is to be installed in a conduit, all cable shall  be pulled in the conduit at the same time. The pulling of a cable through duct banks  or conduits may be accomplished by hand winch or power winch with the use of cable  grips or pulling eyes. Maximum pulling tensions shall be governed by cable manufacturer’s  recommendations. A non-hardening lubricant recommended for the type of cable being  installed shall be used where pulling lubricant is required.
  Contractor shall submit pulling tension values  to the Engineer prior to any cable installation. If required by the Engineer, pulling  tension values for cable pulls shall be monitored by a dynamometer in the presence  of the Engineer. Cable pull tensions shall be recorded by the Contractor and reviewed  by the Engineer. Cables exceeding the maximum allowable pulling tension values shall  be removed and replaced by the Contractor at the Contractor’s expense.
  The manufacturer’s minimum bend radius or the  NEC requirements whichever is more restrictive shall apply. Cable installation,  handling and storage shall be per manufacturer’s recommendations. During cold weather,  particular attention shall be paid to the manufacturer’s minimum installation temperature.  Cable shall not be installed when the temperature is at or below the manufacturer’s  minimum installation temperature. At the Contractor’s option, the Contractor may  submit a plan, for review by the Engineer, for heated storage of the cable and maintenance  of an acceptable cable temperature during installation when temperatures are below  the manufacturer’s minimum cable installation temperature.
  Cable shall not be dragged across base can or  manhole edges, pavement or earth. When cable must be coiled, lay cable out on a  canvas tarp or use other appropriate means to prevent abrasion to the cable jacket.
Engineer may optionally add this language.
108-3.3 INSTALLATION OF DIRECT-BURIED CABLE IN TRENCHES.
Unless  otherwise specified, the Contractor shall not use a cable plow for installing the  cable. Cable shall be unreeled uniformly in place alongside or in the trench and  shall be carefully placed along the bottom of the trench. The cable shall not be  unreeled and pulled into the trench from one end. Slack cable sufficient to provide  strain relief shall be placed in the trench in a series of S curves. Sharp bends  or kinks in the cable shall not be permitted.
Where cables must cross over each other, a minimum  of 3 in vertical displacement shall  be provided with the topmost cable depth at or below the minimum required depth  below finished grade.
Primary airfield lighting cables installed  shall have cable circuit identification markers attached on both sides of each  L-823 connector and on each airport lighting cable entering or leaving cable  access points, such as manholes, handholes, pull boxes, junction boxes, etc. Markers  shall be of sufficient length for imprinting the cable circuit identification legend  on one line, using letters not less than ¼ in in size. The cable circuit identification  shall match the circuits noted on the construction plans.
a. Trenching.Where  turf is well established and the sod can be removed, it shall be carefully stripped  and properly stored. Trenches for cables may be excavated manually or with mechanical  trenching equipment. Walls of trenches shall be essentially vertical so that a minimum  of surface is disturbed. Graders shall not be used to excavate the trench with their  blades. The bottom surface of trenches shall be essentially smooth and free from  coarse aggregate. Unless otherwise specified, cable trenches shall be excavated  to a minimum depth of 18 in  below finished grade, except as follows:
(1)When off the  airport or crossing under a roadway or driveway, the minimum depth shall be 36 in unless otherwise specified.
(2)Minimum cable  depth when crossing under a railroad track, shall be 42 in unless otherwise specified.
Dewatering necessary for cable installation, erosion  and turbidity control, in accordance with Federal, State, and Local requirements  is incidental to its respective pay items as part of Item L-108. The cost of all  excavation regardless of type of material encountered, shall be included in the  unit price bid for the L-108 Item.
The Contractor shall excavate all cable trenches  to a width not less than 6 in.  Unless otherwise specified on the plans, all cables in the same location and running  in the same general direction shall be installed in the same trench.
When rock is encountered, the rock shall be removed  to a depth of at least 3 in  below the required cable depth and it shall be replaced with bedding material of  earth or sand containing no mineral aggregate particles that would be retained on  a 1/4 in sieve. Flowable backfill material  may alternatively be used. The Contractor shall ascertain the type of soil or rock  to be excavated before bidding. All such rock removal shall be performed and paid  for under Item P-152.
Duct bank or conduit markers temporarily removed  for trench excavations shall be replaced as required.
It is the Contractor’s responsibility to locate  existing utilities within the work area prior to excavation. Where existing active  cables cross proposed installations, the Contractor shall insure that these cables  are adequately protected. Where crossings are unavoidable, no splices will be allowed  in the existing cables, except as specified on the plans. Installation of new cable  where such crossings must occur shall proceed as follows:
(1) Existing cables  shall be located manually. Unearthed cables shall be inspected to assure absolutely  no damage has occurred.
(2)Trenching,  etc., in cable areas shall then proceed, with approval of the Engineer, with care  taken to minimize possible damage or disruption of existing cable, including careful  backfilling in area of cable.
In the event that any previously identified cable  is damaged during the course of construction, the Contractor shall be responsible  for the complete repair or replacement.
b. Backfilling.After the cable has been installed, the trench shall be backfilled. The first layer  of backfill in the trench shall be 3 in  deep, loose measurement, and shall be either earth or sand containing no mineral  aggregate particles that would be retained on a 1/4in sieve. This layer shall not be compacted. The second layer shall  be 5 in deep, loose measurement, and  shall contain no particles that would be retained on a 1 in sieve. The remaining 3rd and subsequent  layers of backfill shall not exceed 8 in  of loose measurement and be excavated or imported material and shall not contain  stone or aggregate larger than 4 in  maximum diameter.
The second and subsequent layers shall be thoroughly  tamped and compacted to at least the density of the adjacent undisturbed soil, and  to the satisfaction of the Engineer. If necessary to obtain the desired compaction,  the backfill material shall be moistened or aerated as required.
Trenches shall not contain pools of water during  backfilling operations. The trench shall be completely backfilled and tamped level  with the adjacent surface, except that when turf is to be established over the trench,  the backfilling shall be stopped at an appropriate depth consistent with the type  of turfing operation to be accommodated. A proper allowance for settlement shall  also be provided. Any excess excavated material shall be removed and disposed of  in accordance with the plans and specifications.
Underground electrical warning (caution) tape shall  be installed in the trench above all direct-buried cable. Contractor shall submit  a sample of the proposed warning tape for acceptance by the Engineer. If not shown  on the plans, the warning tape shall be located 6in above the direct-buried cable or the counterpoise wire if present.  A 4-6 in wide polyethylene film detectable  tape, with a metalized foil core, shall be installed above all direct buried cable  or counterpoise. The tape shall be of the color and have a continuous legend as  indicated on the plans. The tape shall be installed 8in minimum below finished grade.
c. Restoration.Where soil and sod has been removed, it shall be replaced as soon as possible after  the backfilling is completed. All areas disturbed by work shall be restored to its  original condition. The restoration shall include the [sodding][topsoiling]  [fertilizing] [liming] [seeding] [sprigging] [mulching]as shown on the plans.  The Contractor shall be held responsible for maintaining all disturbed surfaces  and replacements until final acceptance. When trenching is through paved areas,  restoration shall be equal to existing conditions and compaction shall meet the  requirements of Item P-152. Restoration shall be considered incidental to the pay  item of which it is a component part.
 Engineer to specify the correct method of turfing  and remember to include in the construction documents the appropriate FAA turfing  specification for restoration related to the installation of the power cables.
Under certain conditions, it may be beneficial to install cables by cable plowing. This type of installation method should only be specified where sandy soils are prevalent and with no rocks or other debris that would nick or cut the cable insulation. The engineer should specify the equipment to be used so the cables are placed at a minimum depth of 18 in below finished grade. The cable should be manually unreeled off the spool as the machine travels, such that the earth is not unreeling the spool.
108-3.4 CABLE MARKERS FOR DIRECT-BURIED CABLE.
The location  of direct buried circuits shall be marked by a concrete slab marker, 2 feet (60 cm) square and 4-6in (100 - 150 mm)  thick, extending approximately 1 in  (25 mm) above the surface. Each  cable run from a line of lights and signs to the equipment vault shall be marked  at approximately every 200 feet (60 m)  along the cable run, with an additional marker at each change of direction of cable  run. All other direct-buried cable shall be marked in the same manner. Cable markers  shall be installed directly above the cable. The Contractor shall impress the word  “CABLE” and directional arrows on each cable marking slab. The letters shall be  approximately 4 in (100 mm) high and 3in (75 mm) wide, with  width of stroke 1/2 in (12 mm) and 1/4in (6 mm) deep.
The location of each underground cable connection,  except at lighting units, or isolation transformers, or power adapters shall be  marked by a concrete marker slab placed above the connection. The Contractor shall  impress the word “SPLICE” on each slab. The Contractor also shall impress additional  circuit identification symbols on each slab as directed by the Engineer. All cable  markers and splice markers shall be painted international orange. Paint shall be  specifically manufactured for uncured exterior concrete. Furnishing and installation  of cable markers is incidental to the respective cable pay item.
108-3.5 SPLICING
Connections of the type shown on the plans  shall be made by experienced personnel regularly engaged in this type of work and  shall be made as follows:
a. Cast Splices.These shall be made by using crimp connectors for jointing conductors.  Molds shall be assembled, and the compound shall be mixed and poured in accordance  with manufacturer’s instructions and to the satisfaction of the Engineer.
b. Field-attached Plug-in Splices.These shall be assembled in accordance with manufacturer’s instructions.  These splices shall be made by plugging directly into mating connectors. In all  cases the joint where the connectors come together shall be wrapped with at least  one layer of rubber or synthetic rubber tape and one layer of plastic tape, one-half  lapped, extending at least 1-1/2 in  (37 mm) on each side of the joint.
c. Factory-Molded Plug-in Splices.These shall be made by plugging directly into mating connectors. In  all cases, the joint where the connectors come together shall be wrapped with at  least one layer of rubber or synthetic rubber tape and one layer of plastic tape,  one-half lapped, extending at least 1-1/2in (37 mm) on each  side of the joint.
d. Taped or Heat-Shrinked Splices.A taped splice shall be made in the following manner:
Bring the cables to their final position and  cut so that the conductors will butt. Remove insulation and jacket allowing for  bare conductor of proper length to fit compression sleeve connector with 1/4 in (6mm) of bare conductor on each side of the connector. Prior to splicing,  the two ends of the cable insulation shall be penciled using a tool designed specifically  for this purpose and for cable size and type. Do not use emery paper on splicing  operation since it contains metallic particles. The copper conductors shall be thoroughly  cleaned. Join the conductors by inserting them equidistant into the compression  connection sleeve. Crimp conductors firmly in place with crimping tool that requires  a complete crimp before tool can be removed. Test the crimped connection by pulling  on the cable. Scrape the insulation to assure that the entire surface over which  the tape will be applied (plus 3 in  (75 mm) on each end) is clean. After  scraping wipe the entire area with a clean lint-free cloth. Do not use solvents.
Apply high-voltage rubber tape one-half lapped  over bare conductor. This tape should be tensioned as recommended by the manufacturer.  Voids in the connector area may be eliminated by highly elongating the tape, stretching  it just short of its breaking point. Throughout the rest of the splice less tension  should be used. Always attempt to exactly half-lap to produce a uniform buildup.  Continue buildup to 1-1/2 times cable diameter over the body of the splice with  ends tapered a distance of approximately 1in (25 mm) over the  original jacket. Cover rubber tape with two layers of vinyl pressure-sensitive tape  one-half lapped. Do not use glyptol or lacquer over vinyl tape as they react as  solvents to the tape. No further cable covering or splice boxes are required.
Heat shrinkable tubing shall be installed following  manufacturer’s instructions. Direct flame heating shall not be permitted unless  recommended by the manufacturer. Cable surfaces within the limits of the heat-shrink  application shall be clean and free of contaminates prior to application.
108-3.6 BARE COUNTERPOISE WIRE INSTALLATION FOR LIGHTNING PROTECTION AND GROUNDING.
If shown on the plans or included in the job specifications, bare counterpoise  copper wire shall be installed for lightning protection of the underground cables.  Counterpoise wire shall be installed in the same trench for the entire length of  buried cable, conduits and duct banks that are installed to contain airfield cables.  Where the cable or duct/conduit trench runs parallel to the edge of pavement, the  counterpoise shall be installed in a separate trench located half the distance between  the pavement edge and the cable or duct/conduit trench. In trenches not parallel  to pavement edges, counterpoise wire shall be installed continuously a minimum of  4 in above the cable, conduit or  duct bank, or as shown on the plans if greater. Additionally, counterpoise wire  shall be installed at least 8 in  below the top of subgrade in paved areas or 10 in below finished grade in un-paved areas. This dimension  may be less than 4 in where conduit  is to be embedded in existing pavement. Counterpoise wire shall not be installed  in conduit.
The counterpoise wire shall be routed around  to each light fixture base, mounting stake, or junction/access structures. The counterpoise  wire shall also be exothermically welded to ground rods installed as shown on the  plans but not more than 500 ft  (150 m) apart around the entire  circuit.
The counterpoise system shall be continuous  and terminate at the transformer vault or at the power source. It shall be securely  attached to the vault or equipment external ground ring or other made electrode  grounding system. The connections shall be made as shown on the plans and in the  specifications.
If shown on the plans or in the specifications,  a separate equipment (safety) ground system shall be provided in addition to the  counterpoise wire using one of the following methods:
(1) A ground rod  installed at and securely attached to each light fixture base, mounting stake if  painted, and to all metal surfaces at junction/access structures.
(2) Install an insulated  equipment ground conductor internal to the conduit system and securely attached  it to each light fixture base and to all metal surfaces at junction/access structures.  This equipment ground conductor shall also be exothermically welded to ground rods  installed not more than 500 feet (150 m)  apart around the circuit.
a. Counterpoise Installation Above Multiple  Conduits and Duct Banks.Counterpoise wires shall be  installed above multiple conduits/duct banks for airfield lighting cables, with  the intent being to provide a complete cone of protection over the airfield lighting  cables. When multiple conduits and/or duct banks for airfield cable are installed  in the same trench, the number and location of counterpoise wires above the conduits  shall be adequate to provide a complete cone of protection measured 22 ½ degrees  each side of vertical.
Where duct banks pass under pavement to be constructed  in the project, the counterpoise shall be placed above the duct bank. Reference  details on the construction plans.
b. Counterpoise Installation at Existing Duct  Banks.When airfield lighting cables are indicated on  the plans to be routed through existing duct banks, the new counterpoise wiring  shall be terminated at ground rods at each end of the existing duct bank where the  cables being protected enter and exit the duct bank. The new counterpoise conductor  shall be bonded to the existing counterpoise system.
108-3.7 EXOTHERMIC BONDING.
Bonding of counterpoise wire shall be by the exothermic welding process.  Only personnel experienced in and regularly engaged in this type of work shall make  these connections.
Contractor shall demonstrate to the satisfaction of the Engineer, the  welding kits, materials and procedures to be used for welded connections prior to  any installations in the field. The installations shall comply with the manufacturer’s  recommendations and the following:
a. All slag shall be removed from welds.
b. For welds at light fixture base cans, all galvanized  coated surface areas and “melt” areas, both inside and outside of base cans, damaged  by exothermic bond process shall be restored by coating with a liquid cold-galvanizing  compound conforming to U.S. Navy galvanized repair coating meeting Mil. Spec. MIL-P-21035.  Surfaces to be coated shall be prepared and compound applied in accordance with  manufacturer’s recommendations.
c. All buried copper and weld material at weld  connections shall be thoroughly coated 6 mil of 3M “Scotchkote,” or approved equivalent, or coated with  coal tar Bitumastic® material to prevent surface exposure to corrosive soil or moisture.
108-3.8 TESTING.
The Contractor shall furnish all necessary  equipment and appliances for testing the airport electrical systems and underground  cable circuits before and after installation. The Contractor shall perform all tests  in the presence of the Engineer. The Contractor shall demonstrate the electrical  characteristics to the satisfaction of the Engineer. All costs for testing are incidental  to the respective item being tested. For phased projects, the tests must be completed  by phase and results meeting the specifications below must be maintained by the  Contractor throughout the entire project as well as during the ensuing warranty  period.
Earth resistance testing methods shall be submitted  to the Engineer for approval. Earth resistance testing results shall be recorded  on an approved form and testing shall be performed in the presence of the Engineer.  All such testing shall be at the sole expense of the Contractor.
Should the counterpoise or ground grid conductors  be damaged or suspected of being damaged by construction activities the Contractor  shall test the conductors for continuity with a low resistance ohmmeter. The conductors  shall be isolated such that no parallel path exists and tested for continuity. The  Engineer shall approve of the test method selected. All such testing shall be at  the sole expense of the Contractor.
After installation, the Contractor shall test  and demonstrate to the satisfaction of the Engineer the following:
a.That all affected lighting power and control circuits (existing and new) are continuous and free from  short circuits.
b.That all affected circuits (existing and new) are free from unspecified grounds.
c.That the insulation resistance to ground of all new non-grounded series circuits or cable segments is  not less than 50 megohms.
d.That the insulation resistance to ground of all non-grounded conductors of new multiple circuits or  circuit segments is not less than 50 megohms.
e.That all affected circuits (existing and new) are properly connected in accordance with applicable  wiring diagrams.
f.That all affected circuits (existing and new) are operable. Tests shall be conducted that include  operating each control not less than 10 times and the continuous operation of each  lighting and power circuit for not less than 1/2 hour.
g.That the impedance to ground of each ground rod does not exceed 25 ohms prior to establishing connections  to other ground electrodes. The fall-of-potential ground impedance test shall be  used, as described by ANSI/IEEE Standard 81, to verify this requirement.
Two copies of tabulated results of all cable  tests performed shall be supplied by the Contractor to the Engineer. Where connecting  new cable to existing cable, ground resistance tests shall be performed on the new  cable prior to connection to the existing circuit.
There are no approved “repair” procedures for  items that have failed testing other than complete replacement.
METHOD OF MEASUREMENT
108-4.1Trenching shall be measured by the linear feet (meters) of trench, including  the excavation, backfill, and restoration, completed, measured as excavated, and  accepted as satisfactory.
When specified, separate measurement shall be  made for trenches of various specified widths.
The cost of all excavation, backfill, dewatering  and restoration regardless of the type of material encountered shall be included  in the unit price bid for the work.
108-4.2Cable or counterpoise wire installed in trench, duct bank or conduit  shall be measured by the number of linear feet (meters) of cable or counterpoise  wire installed in trenches, duct bank or conduit, including ground rods and grounding  connectors, and trench marking tape ready for operation, and accepted as satisfactory.  Separate measurement shall be made for each cable or counterpoise wire installed  in trench, duct bank or conduit. The measurement for this item [shall] [shall not]include additional quantities  required for slack.
 
Engineer to decide  if the quantity of cable provided in the bid tabulations includes an estimated quantity  for slack. If so, this should be clearly identified on the plans and specifications.  If not, add the following language at the end of paragraph 108-4.2:
“Cable and counterpoise  slack is considered incidental to this item and is included in the contractor’s  unit price. No separate measurement or payment will be made for cable or counterpoise  slack.”
 
BASIS OF PAYMENT
108-5.1Payment will be made at the contract unit price for trenching, cable and bare counterpoise wire installed in trench (direct-buried), or cable and equipment ground installed in duct bank or conduit, in place by the Contractor and accepted by the Engineer. This price shall be full compensation for furnishing all materials and for all preparation and installation of these materials, and for all labor, equipment, tools, and incidentals, including ground rods and ground connectors and trench marking tape, necessary to complete this item.Payment will be made under:
| Item L-108-5.1 | Trenching for direct-buried cable -per linear foot (meter) | 
| Item L-108-5.2 | [No. 8 AWG] [No. 6 AWG]L-824C Cable, installed in trench, duct bank or conduit-per liner foot (meter) | 
Engineer to specify appropriate size of cable. If more than one size is required on the project, provide additional item nos.; one for each size and type.
| Item L-108-5.3 | Bare Counterpoise Wire, installed in trench, duct bank or conduit, including ground rods and ground connectors-per linear foot (meter) | 
| Item L-108-5.4 | Bare or insulated equipment ground, installed in duct bank or conduit including ground rods and ground conductors – per linear foot (meter). | 
MATERIAL REQUIREMENTS
| AC 150/5345-7 | Specification for L-824 Underground Electrical Cable for Airport Lighting Circuits | 
| AC 150/5345-26 | Specification for L-823 Plug and Receptacle Cable Connectors | 
| FED SPEC J-C-30 | Cable and Wire, Electrical Power, Fixed Installation (cancelled; replaced by A-A-59544 Cable and Wire, Electrical (Power, Fixed Installation)) | 
| FED SPEC A-A-55809 | Insulation Tape, Electrical, Pressure-Sensitive Adhesive, Plastic | 
| ASTM B 3 | Soft or Annealed Copper Wire | 
| ASTM D 4388 | Rubber tapes, Nonmetallic Semiconducting and Electrically Insulating | 
REFERENCE DOCUMENTS
| NFPA No. 70NFPA No. 70 | National Electrical Code (NEC) | 
| MIL-S-23586C | Sealing Compound, Electrical, Silicone Rubber | 
| NN | Building Industry Consulting Service International(BICSI) | 
| ANSI/IEEE Std 81 | IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System | 
